820/826 Dogwood St, 615/617/633 Lea Ave, CoquitlamRental (not a presale)
Stage reached: Rezoning application submitted, 2021-10-14. This project is not currently being marketed: there are no prices, no reservations and nothing for sale on this page.
Updated
Key facts
- Current stage
- Rezoning application submitted, 2021-10-14As of · Source: City of Coquitlam record
- First record on file
- Rezoning application submitted, 2021-10-14As of · Source: City of Coquitlam record
- Stage records on file
- 1As of · Source: City of Coquitlam records
- Municipality
- City of CoquitlamAs of · Source: City of Coquitlam record
- Applicant (as in the record)
- WG Architecture Inc.As of · Source: City of Coquitlam record
- Proposed units
- 204As of · Source: City of Coquitlam record
- Tallest building proposed
- 12 storeysAs of · Source: City of Coquitlam record
- File numbers
- 21-145As of · Source: City of Coquitlam record
Stage history
- Rezoning application submitted, 2021-10-14. Municipal record (first seen 2026-11-13)
First sourced record: Rezoning application submitted, 2021-10-14.
What happens next
In a typical municipal approval the stages that follow are, in order: first and second reading, then public hearing, then third reading, then rezoning adopted, then development permit application submitted, then development permit issued, then building permit application submitted, then building permit issued, then under construction, then completed. This is the usual order, not a forecast: a project can stop, be amended or take any length of time.
How does it compare with other Coquitlam projects?
| Approval stage | Projects | Latest stage date on record |
|---|---|---|
| Pre-application | 4 | 2026-11-06 |
| Rezoning application submitted (this project) | 7 | 2025-10-24 |
| Development permit application submitted | 80 | 2026-09-29 |
| All projects | 91 |
820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam: frequently asked questions
What approval stage is 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam at?
Rezoning application submitted, 2021-10-14. This is the latest stage in the City of Coquitlam record, last seen 2026-11-13.
When was 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam first recorded?
The first record on file is "Rezoning application submitted", 2021-10-14. We first saw it on 2026-11-13.
How many homes are proposed at 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam?
204 homes, as stated in the municipal record (seen 2026-11-13).
How tall is the proposed building at 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam?
The tallest building is proposed at 12 storeys, per the municipal record (seen 2026-11-13).
Who is the applicant for 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam?
WG Architecture Inc., as named in the municipal record. We do not infer a developer from other sources.
Is 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam for sale?
It is listed as purpose-built rental, not a presale, so there is nothing to buy through a presale contract.
What happens next at 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam?
In a typical municipal approval the stages that follow are, in order: first and second reading, then public hearing, then third reading, then rezoning adopted, then development permit application submitted, then development permit issued, then building permit application submitted, then building permit issued, then under construction, then completed. This is the usual order, not a forecast: a project can stop, be amended or take any length of time.
Where does the information on 820/826 Dogwood St, 615/617/633 Lea Ave, Coquitlam come from?
From City of Coquitlam records. Each stage links to its record, and the data was last seen on 2026-11-13.
How many presale projects are in Coquitlam?
78 presale projects in Coquitlam appear in municipal records as of 2026-11-13. Read more
Contains information licensed under the Open Government Licence – Coquitlam. The municipalities do not endorse this site. Facts are summarised from public records and linked to their source.